Date: May 25, 2013
Lot 67, our dirt.
Date: June 4, 2013.
Trenches for drains going in.
Date: June 22, 2013
Foundation has been poured!
Date: June 26, 2013
Laying the wood out for framing.
Date: June 29, 2013
The frame going up.
Date: July 2, 2013
More framing of interior walls.
Date: July 13, 2013
Floors, counters and cabinet selections!
Date: July 24, 2013
Second floor and a roof!
Date: August 7, 2013
Roof tiles!
Date: August 11, 2013
"Dusty Shoe" walk thru
Kitchen | Garage |Stairs
Family Room | Sliding Door | Dining Room
Master Bedroom w/ Bathtub & Shower enclosure
Me | Lil'bug | Mom-in-Law in our front door
Date: September 12, 2013
Under layer for the stucco to stick to. And windows!
Date: September 20, 2013
This date is significant because we were supposed to be moved in by now! But instead the house looks like this. We are hoping and praying to at least spend Thanksgiving in the house since Lil' Bug's first birthday and Halloween are scratched off the list. Fingers crossed...
Date: November 8, 2013
Good news! The house is SOOOO close to being done, we can taste it! We got to do a walk thru and nit-pick the little details we want fixed. It was great to see it all put together. My decorator wheels are really spinning now. Here's a few shots.
I can almost smell all the holiday baking that will happen here!
Yeah, it faces west. That's a problem. Time to invest in some good window coverings.
Lil'Bug loves to play on those stairs! And I have a lot of painting to do. Gray?
I might actually take a bath here! Bubbles, candles, vino....
The front is plain now, but a little extra landscaping and some porch decor, it'll be all spruced up.
So we are about 3 weeks 'til moving day. I just hope we are settled enough for a Thanksgiving turkey and not just a quick Costco rotisserie chicken!